Hydrogen Turbines Follow On - Scenario 10 Results Spreadsheet - GB Capacity Mix Optimisation - Results


Citation Mavropoulos, S. Hydrogen Turbines Follow On - Scenario 10 Results Spreadsheet - GB Capacity Mix Optimisation - Results, ETI, 2017. https://doi.org/10.5286/UKERC.EDC.000196.
Cite this using DataCite
Author(s) Mavropoulos, S.
Project partner(s) Baringa Partners LLP
Publisher ETI
DOI https://doi.org/10.5286/UKERC.EDC.000196
Download AdHoc_CCS_CC1011_5.xlsx document type
Abstract Various scenarios for the UK’s power fleet composition in 2030 and 2040 were developed. Dispatch modelling in Plexos was carried out by Baringa on these fleets to investigate the role gas fed plants might have in future. This includes the ability to study load factors, stop/starts etc, and together with concomitant pricing, provide a picture of investment remuneration. The effect of key drivers is studied e.g. gas price.

The purpose of this spreadsheet is to provide:
  1. The pathway results (capacity, generation ,costs) for all scenarios. The pathway results are the output of the capacity optimisation model (LT: Long-Term)
  2. Levelised cost of electricity and value of capacity for the Base Case (Model LT: Long-Term)
  3. Detailed dispatch results for the Base Case for a spot year (2030). The dispatch results have been simulated with the full year dispatch model (ST: Short-Term)
  4. Dispatch reults for two spot years (2030, 2050) for the rest of the scenarios. These results were simulated with the capacity optimisation model (LT)
  5. Comparisons between the Base Case and sensitivities
  6. Comparisons between Base Case and other GB scenarios
Associated Project(s) ETI-CC1011: Salt Cavern Appraisal for Hydrogen Power Generation Systems
Associated Dataset(s) No associated datasets
Associated Publication(s)

Hydrogen Turbines Follow On - A Review of Selected New CO2 Capture Technologies

Hydrogen Turbines Follow On - Assessment of LMS 100 Heat Management Options and Techno-Economic Parameters of Gas Turbine Power Plants

Hydrogen Turbines Follow On - CCS and H2 Dispatch modelling - Market and asset modelling results for Scenario 3 and Baringa Reference Case

Hydrogen Turbines Follow On - CCS and H2 Dispatch modelling - Scenarios 1 & 2 Results Pack

Hydrogen Turbines Follow On - CCS and H2 Dispatch modelling - Scenarios 3 & 4 Results Spreadsheet

Hydrogen Turbines Follow On - CCS and H2 GT Dispatch modelling scenario 1 and 2 results spreadsheet

Hydrogen Turbines Follow On - Power Sector CCS and H2 Turbine Asset Modelling - Central Decarb market modelling results

Hydrogen Turbines Follow On - Review of Gas Turbines and their Ability to use Hydrogen-Containing Fuel Gas

Hydrogen Turbines Follow On - Salt Cavern Appraisal for Hydrogen and Gas Storage - Appendices

Hydrogen Turbines Follow On - Salt Cavern Appraisal for Hydrogen and Gas Storage - Final Report

Hydrogen Turbines Follow On - Scenario 10 Results Pack - Cost-optimal pathways to decarbonising the GB power sector - Final Report

Hydrogen Turbines Follow On - Scenario 1,2 and 3 Results Spreadsheet: Role of Gas/H2 in the GB power sector - initial analysis

Hydrogen Turbines Follow On - Scenario 5 Results Pack - Power sector CCS and H2 Turbine Asset Modelling

Hydrogen Turbines Follow On - Scenario 5 Results Spreadsheet

Hydrogen Turbines Follow On - Scenarios 1,2 and 3 Results Pack Report - The role of Gas/H2 in the GB power sector - initial analysis