Reference Number | W/61/00641/00/00 | |
Title | Merlin Offshore Wind Turbine System - Phase 1 | |
Status | Completed | |
Energy Categories | Renewable Energy Sources (Wind Energy) 100%; | |
Research Types | Applied Research and Development 100% | |
Science and Technology Fields | ENGINEERING AND TECHNOLOGY 100% | |
UKERC Cross Cutting Characterisation | Not Cross-cutting 100% | |
Principal Investigator |
Dr A (Tony ) Trapp No email address given The Engineering Business Ltd |
|
Award Type | Standard | |
Funding Source | DTI | |
Start Date | 01 September 2003 | |
End Date | 30 June 2004 | |
Duration | 9 months | |
Total Grant Value | £129,597 | |
Industrial Sectors | Power | |
Region | North East | |
Programme | WIND | |
Investigators | Principal Investigator | Dr A (Tony ) Trapp , The Engineering Business Ltd (100.000%) |
Web Site | ||
Objectives | The Merlin Wind Turbine Installation System has been designed and patented by The Engineering Business Ltd (EB). This project, phase 1 of the development, comprises a feasibility study carried out by EB, and part funded by the DTI with the key objective of: Investigating the technical and economical viability of the Merlin system as an alternative technique for installing offshore wind turbines. Total project cost = 189545, DTI grant = 129597 | |
Abstract | ||
Data | No related datasets |
|
Projects | No related projects |
|
Publications | Merlin Offshore Wind Turbine Installation System: Final Report |
|