Projects: Custom Search |
||
Reference Number | B/T1/00809/00/00 | |
Title | 100kWe Biomass fuelled indirect fired Micro Turbine | |
Status | Completed | |
Energy Categories | Other Power and Storage Technologies (Electric power conversion) 20%; Renewable Energy Sources (Bio-Energy, Applications for heat and electricity) 80%; |
|
Research Types | Applied Research and Development 100% | |
Science and Technology Fields | ENGINEERING AND TECHNOLOGY 100% | |
UKERC Cross Cutting Characterisation | Not Cross-cutting 100% | |
Principal Investigator |
Project Contact No email address given Talbotts Heating Limited |
|
Award Type | Grant - Non VAT | |
Funding Source | DTI | |
Start Date | 29 October 2004 | |
End Date | 31 October 2006 | |
Duration | 24 months | |
Total Grant Value | £296,774 | |
Total Project Value | £1,389,644 | |
Industrial Sectors | Power | |
Region | West Midlands | |
Programme | BIO-MASS | |
Investigators | Principal Investigator | Project Contact , Talbotts Heating Limited (100.000%) |
Web Site | ||
Objectives | The aim of this project was to further develop micro turbine indirect firing and to develop this into a biomass generator, building on the success of the previous project. The system was redesigned and rebuilt using the experience gained and the recommendations reported in our last project. The efficiency, maintenance and safety of the system was improved through this development project. Total project cost = 1389644. DTI Grant was 296774. | |
Abstract | None available | |
Data | No related datasets |
|
Projects | No related projects |
|
Publications | ||
Added to Database | 01/01/07 |