go to top scroll for more

Network Capacity - Performance of Onshore Multi-Terminal HVDC: WP2 Tasks 2 & 3


Citation Mott MacDonald Network Capacity - Performance of Onshore Multi-Terminal HVDC: WP2 Tasks 2 & 3, ETI, 2010. https://doi.org/10.5286/UKERC.EDC.000683.
Cite this using DataCite
Author(s) Mott MacDonald
Project partner(s) Mott MacDonald
Publisher ETI
DOI https://doi.org/10.5286/UKERC.EDC.000683
Download ESD_EN2002_5.pdf document type
Abstract The UK’s electricity transmission and distribution systems have little spare capacity to accommodate the widespread changes in volume and location of power flows arising from planned changes in generation type and characteristics, and from major changes in demand patterns. Gaining consents for the construction of new overhead lines is extremely time-consuming and costly. Without action, this will increasingly constrain the necessary changes in generation and demand.

The ‘Network Capacity’ project has assessed the feasibility of using new technologies now emerging in the marketplace or in development, including multi-terminal HVDC systems, in novel ways in order to provide increased Transmission & Distribution system capacity and improved management of network power flows, in order to facilitate increased renewable energy installation levels in the UK.

This document contains two studies conducted to assess the performance and impact of multi-terminal High Voltage Direct Current systems integrated into the UK’s onshore transmission system:
  • Appendix A: TransGrid Solutions Report : Assessment of Performance of Onshore HVDC Systems Integrated into the UK AC Grid (WP2 Task 2; starts on page 12)
    This study looked at integrating HVdc technology into the UK grid by converting existing HVac lines into HVdc lines in order to improve the transmission capacity in selected transmission corridors. The outcome of this study is a qualitative assessment that evaluates the performance of the system following the conversion of selected AC lines to Voltage Source Converter (VSC) HVdc and Line-Commutated Converter (LCC) HVdc, and makes a comparison with the performance of the system without the line conversions. Each line conversion scenario therefore compared three schemes: VSC HVdc, LCC HVdc and AC. Schemes were compared exclusively in terms of their relative impact on transmission system performance, rather than on aspects such as cost or environmental impact.
  • Appendix B: Impact of new onshore multi-terminal HVDC (WP 2 Task 3; starts on page 108)
    This report has focused on evaluating the impact of replacing an existing HVAC transmission circuit with an HVDC scheme. As can be seen in section 2.2.3, the required post-fault ratings, for a UK 400 kV double circuit transmission corridor, are in excess of 4 GW. In complying with SQSS specifications, there is negligible benefit of attempting to increase this transmission corridor capacity by replacing it with an onshore HVDC scheme primarily due to economic reasons. The benefits of using an onshore HVDC scheme could be maximised by installing a lowerrating (<4 GW) onshore HVDC cable link in parallel with an existing transmission corridor. However the impact of this application has not been studied as part of this report.
Associated Project(s) ETI-EN2002: Network Capacity
Associated Dataset(s) No associated datasets
Associated Publication(s)

An ETI Perspective - Low carbon challenges for UK energy networks

ETI Insights Report - UK Networks Transition Challenges - Electricity

ETI Insights Report - UK Networks Transition Challenges - Gas

ETI Insights Report - UK Networks Transition Challenges - Heat

ETI Insights Report - UK Networks Transition Challenges - Hydrogen

Enabling efficient networks for low carbon futures: Options for governance and regulation

Infographic - UK Networks Transition Challenges

Network Capacity - Barriers to Application of Multi-Terminal HVDC in the UK: WP2 Task 4

Network Capacity - Barriers to Deployment; and Environmental & Social Impacts of Deployment: WP1 Tasks 4 & 5

Network Capacity - Executive Summary

Network Capacity - Feasibility Assessment of Onshore Multi-Terminal High Voltage Direct Current (HVDC) Systems in the UK

Network Capacity - Final Project Summary (Work Packages 1 & 2 a.k.a. WP1 Task 8)

Network Capacity - One Page Summary

Network Capacity - Request for Proposal

Network Capacity - Technology Options, Benefits & Barriers Workshop and Multi-Criteria Assessment: WP1 Tasks 6 & 7

Network Capacity - WP1 Task 1: Assessment of Power Electronic Technologies - A literature review of the relevant power electronic technologies

Network Capacity -WP1 Task 2: Impact of Active Power Flow Management Solutions

Options Choices Actions - UK scenarios for a low carbon energy system

The Networks Jigsaw Event

UK Networks Transition Challenges - A Systems View